Most townhouse buyers in Queensland focus on the kitchen, the floor plan and the settlement date, then discover months later that the driveway is cracking, the stormwater pits are blocked and the visitor parking bays were never line-marked. Those problems sit on common property, the shared areas the body corporate looks after, and they are often the first defects a new committee has to chase. A townhouse body corporate inspection in Queensland has to cover those shared areas, not just the lot. This guide sets out what gets inspected on common property, who is responsible for each type of defect, and how to get the paperwork right before control of the scheme changes hands.

Table of Contents

Quick Takeaways

Key Insight Explanation
Common property is defined by the registered plan Check the plan and community management statement before you walk the site, so you know exactly which driveways, fences and walls the body corporate maintains.
Fees fund common property only Damage confined to one lot usually falls to that lot owner. Mark the lot boundary on your site sketch so the split is recorded at inspection, not argued about later.
Water causes most common area defects Check gutters for fall toward outlets and confirm every downpipe discharges into stormwater, not onto a driveway or a neighbouring lot.
Balcony boundary items need a confirmed owner Responsibility for balustrade elements on a balcony boundary can differ between schemes. Confirm it against the scheme documents before you assign the defect.
Safety items come first The body corporate must maintain common property in a safe condition. Balustrades, handrails, stair nosings and lighting belong at the top of every defect list.
Record defects before control changes hands Once the developer’s control ends, the new committee inherits whatever was not written down. Lodge the defect list while the builder is still engaged.
Insurance has limits Body corporate insurance generally covers common property and building structure, not personal contents or lot fixtures. Read the policy schedule before you rely on it.

What Counts as Common Property in a Townhouse Scheme

Common property is the part of a scheme the body corporate maintains, and it is defined by the registered plan rather than by what a buyer assumes is shared. In a townhouse development that usually covers driveways, shared pathways, visitor parking bays, perimeter fences, landscaping, and the stormwater network serving the whole site. Anything not included within a lot on the plan generally falls into this category.

Inspector checks driveway and visitor parking bays in a new townhouse complex, a common area for body corporate inspection in Queensland.

Reading the plan and the community management statement

Before you walk a site, pull the registered plan and the community management statement. The plan shows where each lot boundary sits, and the statement sets out which items the body corporate is responsible for maintaining. If the two documents do not agree, that disagreement is a problem in its own right and needs to be raised before the scheme changes hands.

In practice, I start with the plan and mark every lot boundary on a site sketch. That sketch becomes the reference point for the rest of the inspection, because it stops arguments later about whether a crack sits inside a lot or on common property.

Pro tip: Photograph each boundary marker and fence line on the day of inspection, with the plan open beside the camera frame, so your photo record matches the legal description.

Shared walls, fences and retaining structures

Shared walls cause the most confusion in townhouses. Whether a party wall, boundary fence or retaining wall is common property depends on how the plan and scheme documents describe it, and the answer is not always the same across two schemes built by the same developer. Do not assume a wall is shared, or that it belongs to the lot, until you have read the documents.

The cost of getting this wrong is real. A retaining wall that the body corporate is expected to repair can become a large bill if it turns out to belong to a lot, or the reverse. Settle the question at inspection, not after the first major repair.

What Gets Inspected on Common Areas

A proper inspection of common property covers every element the body corporate must maintain in a safe, working condition. Under the Body Corporate and Community Management Act, the body corporate has to maintain common property, and that includes keeping it safe. Your inspection should be built around that duty, which is why safety items sit at the top of the list.

Roofs, gutters and downpipes

Water is the most common source of defects I find in townhouse common areas. Check gutters for fall toward the outlets, look for sagging sections, and confirm that every downpipe discharges into the stormwater system rather than onto a neighbouring lot or a paved path. A downpipe that spills onto a driveway is a defect even when the gutter looks fine.

Look closely at roof edges, fascia boards and flashings where they meet walls. These junctions are where water gets in, and they are easy to miss if you only look at the roof from ground level. Use a ladder or a drone where access allows, and record the access method for each point in your report.

Balustrades, handrails and stairs

Balustrades and handrails are the safety items I check first, because a failure here can injure someone. Measure gaps in balustrades, check that handrails are firmly fixed, and test stair nosings for movement. Note any loose fixings and any finish that has started to flake, since corrosion usually starts at the fixing point.

Balcony boundaries need particular attention. Depending on the scheme and how it was built, responsibility for balustrade elements on the balcony boundary may sit with the body corporate rather than the lot owner, so check the scheme documents before you assign the defect to anyone.

Driveways, visitor parking and line marking

Driveways and visitor bays are where cracking shows up first. Look for cracks wider than hairline, trip points at joints, and ponding that remains after rain. Visitor parking bays should be line-marked to the approved layout, with bay numbers and signage in place, because a missing bay is an easy item to fix during the defect period and a harder one afterwards.

Who Is Responsible for Each Defect

Responsibility comes down to two questions: where the defect sits, and what caused it. The location tells you whether the item belongs to common property or to a lot. The cause tells you whether the builder, a trade, or the owner should carry the cost. Mixing up the two is one of the most common reasons defect claims stall.

Body corporate responsibilities

The body corporate is responsible for common property, and fees collected from all owners pay for its maintenance. A lift repair in an apartment block is the standard example, and the same logic applies to a shared driveway in a townhouse scheme. Repairs that benefit only one lot are not paid from the common fund, which is why the boundary between lot and common property matters so much.

Insurance follows the same split. Body corporate insurance generally covers common property and the building structure the scheme is responsible for, but it does not cover personal property or the fixtures inside a lot. Read the policy schedule and check what is listed, because the schedule is the document that will decide a claim.

Lot owner responsibilities

Everything inside the lot is generally the owner’s responsibility, including internal finishes, appliances and fixtures. A leak that starts in your bathroom and damages a neighbouring lot is usually your cost, unless the cause is traced to common property. Owners also maintain their own windows, doors and courtyards in line with the scheme’s by-laws.

Many disputes come from the boundary between the two. External window frames and structural openings are a good example. In many schemes the body corporate is responsible for those elements, while the owner handles other window components, so read the scheme’s responsibility schedule rather than relying on a general rule.

The builder during the defect period

During the defect period, the builder remains liable for defects in the work it carried out, whether those defects sit in a lot or in common property. Queensland’s building framework gives different warranty periods for structural and non-structural defects, and the clock depends on when the work was completed. Get that timeline confirmed in writing before you lodge the report.

A common mistake is treating the builder’s defect period as optional, then waiting for the new committee to raise items. Once the developer hands over control, your negotiating position with the builder weakens. Lodge the report while the builder is still engaged, and ask for a written rectification schedule with dates.

Typical Common Area Defects in New Townhouse Schemes

New townhouse schemes tend to produce the same handful of defects, and most of them are inexpensive to fix if they are caught early. The expensive ones are the ones hidden behind finishes that only show up after the first wet season. Knowing where to look saves time on every inspection.

Drainage is the category I see most often. Many of the problems that appear in the first year trace back to a gradient that was set wrong or a pit that was never connected properly, so it pays to inspect those items before anything else.

Inspector photographs a stormwater pit in the shared garden of a new Brisbane townhouse scheme, recording a common area defect.

Stormwater and drainage faults

Stormwater pits installed without the right gradient hold water, and grates set too high leave a lip that catches debris. Check that pits are clear, that grates sit flush, and that the surrounding surface drains toward them. Water still sitting in a pit or on a path well after the rain has stopped is a clear sign of a gradient problem.

Subsoil drains and retaining wall weepholes are the hidden parts. If they are blocked or missing, the wall will bulge or stain. These items are rarely visible on the day, so ask the builder for drainage plans and check the installed works against them.

Cracking in paths, driveways and retaining walls

Some cracking is normal shrinkage, and some is structural. The test I use is simple: is the crack getting wider, offset across a joint, or running through a load-bearing element? Cracks that open at a joint, step between slabs, or track through a retaining wall need a formal assessment, not a patch.

Record every crack with a photo, a tape measurement and a sketch that shows its position against a fixed reference, such as a lot boundary or a light pole. A crack without a measurement is easy for a builder to dismiss at the first defect meeting.

Landscaping and irrigation left unfinished

Landscaping is often the last item completed, and it is the item most often left half-finished at handover. Check that garden beds are edged, that turf has taken, and that irrigation heads are aligned and not spraying onto paths or walls. An irrigation system that sprays a fence is a fast way to create a moisture defect in the adjoining lot.

Inspection Approaches Compared

Owners and developers usually end up choosing between three approaches. Each one answers a different question, and none of them replaces the others. The table below sets out where each one is strong and where it leaves gaps.

Approach What It Covers Where It Falls Short
Developer practical completion walk Visible finishes and items the builder has already signed off as complete The builder inspects its own work, and common property items are often recorded as minor or deferred
Independent pre-handover inspection Lot and common property, with photos, defect locations and responsibility assigned to specific trades Only as useful as the report that follows, so the written defect list must be followed up before settlement
Body corporate records review Committee minutes, maintenance history, insurance schedules and any earlier defect notices Shows what has been reported, not what is physically wrong on site

In practice, the strongest result comes from combining all three. The records review shows what has already been raised, the independent inspection shows what is physically present, and the builder walk shows what has been accepted. Relying on the developer walk alone is the most common way common property defects go unrecorded.

If you are buying close to settlement, the independent inspection gives you the most useful document, because it is the one you can act on. It lists each defect, names the trade responsible and gives you a record that stands apart from the sales process.

Handover Timing Before Committee Control Changes

Timing is where most townhouse owners lose ground. While the developer still controls the body corporate, defect requests go to a party with a strong interest in closing them quickly. Once the scheme passes to owner control, the new committee has to decide what to chase, often with limited records and no history of the problems.

Why the first general meeting matters

The first general meeting is where the new committee starts to form, and its early decisions about maintenance and defects shape the next several years. If defects were not listed in writing before that meeting, they are unlikely to appear on the agenda. A committee can only act on what it knows about.

Ask for the defect list to be tabled and minuted, so every outstanding item has a record. A minute that says a defect was raised, with the date and the responsible trade, is far stronger than a verbal assurance from the site manager.

What to request before settlement

Before settlement, request the maintenance manuals, warranties for the common property works, the drainage and stormwater plans, and the scheme’s current insurance certificate. These documents are what the new committee will rely on in its first year, and they are rarely complete on handover day.

Defects that are not written down during handover are usually paid for later by whoever is holding the scheme at the time.

Pro tip: Ask for the defect list in the same format as your independent report, with an item number, location, responsible trade and rectification date for each entry. A list in that format is far easier for a committee to track.

Documenting and Escalating Defects

A defect is only as useful as the record behind it. The goal of documentation is to make each item difficult to dispute at the next meeting, whether that meeting is with the builder, the committee or the insurer. Good records also shorten the time between the report and the repair.

Inspection checklist and folder on a wall in front of new townhouses, illustrating handover paperwork for a body corporate scheme.

Writing a defect report the committee can act on

Each entry should state the location, the defect, the photo reference, the likely cause and the trade you believe is responsible. Avoid vague wording such as “poor finish” and describe what you can see, such as “gap at the base of the balustrade post, visible from the footpath side”. Specific wording leaves less room for a trade to argue the point.

Group items by responsibility rather than by location, so the committee can send one notice to each trade. A report that mixes waterproofing, landscaping and door hardware in a single list is harder to action than three short lists sent to three responsible parties.

Escalating when the builder stalls

If a defect is not rectified within the agreed timeframe, follow up in writing and attach the original report. Escalate in steps: a formal request, then a reminder with a firm deadline, then whatever dispute pathway applies to your situation. Each step should refer to the earlier correspondence so the trail is clear.

Specialist advice matters once a dispute turns on responsibility for a structural or safety item. The sources listed below set out the general framework, but the outcome depends on your scheme documents and the facts of your particular defect.

Pro tip: Set up one shared folder for every photo, report and email about common property defects, and name each file with the date and item number. A committee that changes hands every year loses its history quickly without one.

Frequently Asked Questions

Who pays for defects on common property in a townhouse scheme?

The body corporate pays for common property defects from fees collected across the scheme, but a defect that is still within the builder’s defect period should be directed to the builder first. Get responsibility confirmed in writing before you assume the cost falls on owners.

Does a body corporate inspection cover the inside of my townhouse?

A body corporate inspection focuses on common property, but a pre-settlement or pre-handover inspection can cover both the lot and the shared areas. Ask for lot and common property items to be listed separately so responsibility for each is clear.

Can I inspect common property before I buy into a townhouse scheme?

You can, and you should. A pre-purchase walk of common property is usually arranged through the seller or agent, and a records review of committee minutes and insurance schedules is useful alongside the physical inspection. If the scheme is already operating, look for recent maintenance notices as well.

What is the most common common area defect in new townhouses?

In my experience, drainage and water management issues are the most frequent, followed by cracking in paths and driveways. Gutters, downpipes and stormwater pits are where I find the most avoidable problems.

Is body corporate insurance enough to cover a common area defect?

Body corporate insurance generally covers the common property and building structure the scheme is responsible for, but it is not a substitute for the builder’s obligations during the defect period. Insurance is a backstop for damage, not a replacement for the builder’s warranty. Check the policy schedule and confirm what the builder must rectify.

If you have bought into a townhouse scheme or managed a new one, tell us what you found on common property that nobody wrote down, and how long it took to get fixed.