The water was off when we inspected a new apartment. We could still record a chipped tile in front of the linen cupboard and damaged laminate on a powder-room vanity. But the report had to tell the project team something else, too: there was no water available on the day. The chip was a finding. The water being off was a condition that limited the inspection. Those two entries needed different follow-up.
That distinction is useful when you’re weighing up a builder walkthrough versus an independent handover inspection. The walkthrough is where you and your builder discuss the finished work, demonstrations and outstanding items. An independent inspection adds a separate record of what the inspector could see and assess within the agreed scope. Bring that record to the conversation so both sides can work from the same locations and observations.
What does the builder’s final walkthrough cover?
It’s your chance to go through the home with the builder or site supervisor and talk about what’s complete, what’s still outstanding and how the finished home works. Bring your plans, agreed inclusions and any variations you want to check. Ask the builder to demonstrate things you’ll need to use, such as the garage remote, window locks or controls supplied with the home.
The builder’s own site supervision and quality control happen throughout the build. That’s different from the joint walkthrough, when the owner can ask questions and discuss what needs attention. QBCC’s Queensland handover guidance describes using a defects document for agreed minor defects or omissions, noting when the builder will attend to them and listing separately any items the owner raises that aren’t agreed. Bring a copy of your inspection report if you have one, and make sure the outcome of the discussion is recorded.
What does an independent handover inspector add?
An independent inspector can assess visible workmanship, damage and incomplete work in the agreed areas they can safely access. The report gives the builder a location, an observation and, where useful, a photograph. It also helps you separate an observed problem from something that couldn’t be checked. GoInspect doesn’t routinely test appliances, and a visual inspection cannot establish the condition of concealed work.
You may hear this booked as a pre-handover inspection or a practical completion inspection (PCI). Ask exactly what the appointment covers and who will attend, because your builder may also use “PCI” for their meeting with you. The independent report helps inform that meeting. It cannot decide whether you’ve reached practical completion under your contract.
One apartment report, two different next steps
The sample apartment report identified the hallway chip by a fixed reference: the linen cupboard. A tiler could find the right tile even if the tape marking it came off. The report separately marked the corner of a powder-room vanity where the laminate was chipped, giving the cabinet maker a different item to review. Neither observation required water to be available.

There was also a separate note that the water was off at the time of inspection. That’s useful information for the builder and buyer because it tells them what needs another conversation. Ask when the supply will be available and how any checks that depended on it will be arranged. Don’t carry the water note into the defects list as a confirmed leak, or treat it as evidence that the plumbing was checked and passed. The sample report records what was found on the day; it doesn’t tell us whether a later check or repair took place.
The same approach helps a site team finishing a block of apartments. A chip belongs on the work list for the relevant unit and trade. A service that isn’t available belongs on an access or readiness list so you can decide when to revisit the affected checks. Keeping those lists distinct gives trades clear work and helps the site supervisor see what still needs to be made available.
For the meeting, write the two entries differently. For the tile, record “Hallway, in front of linen cupboard: chipped floor tile; tiler to review” and attach the photo. For the water, write “Water off during inspection; confirm when supply will be on and agree which checks will be revisited.” The first makes a visible issue easy to locate. The second makes an unfinished check easy to follow up.
Where the building certifier fits
The building certifier has a separate statutory role in building approvals and required inspections. Ask your builder or certifier which approvals and final documents apply to your property. A builder demonstration, a photo of finished work and an independent defect report are useful for different reasons; none replaces the relevant certification or occupancy documents.
How to get more out of both appointments
- Confirm what will be ready. Check access, cleaning and whether power and water will be available. For an apartment, ask which areas are included, such as the balcony, car space or storage, and who can arrange a separate review of shared areas.
- Agree on the sequence. Where possible, book the independent inspection when the work is ready to assess and leave time to read the findings before the builder walkthrough. If the order has to change, agree how you’ll share and discuss any later findings.
- Record what was and wasn’t checked. Use a room name, a fixed reference and a photo for a visible item. For an unchecked item, write down why it wasn’t checked and what needs to happen before it can be.
- Leave with a plan for follow-up. Confirm who will respond to each point, how access will work and how you’ll check that agreed work has been attended to. Keep the original observations alongside any response or later photos so there’s a clear record.
If you’re preparing your own walkthrough, use GoInspect’s room-by-room PCI checklist. If you’d like a separate report to bring to the discussion, check your handover inspection options and confirm what will be accessible on the day.