An apartment common-area inspection should treat corridors, lift lobbies and stairs as defined project areas, with each visible finding tied to a building, level and recognisable location. For builders and developers, that makes the report usable: the site team can separate a corridor finish item from a stair-cleaning task, send each finding to the relevant trade and keep later checks connected to the original record.

Include indoor shared areas expressly in the inspection brief. In a new-build apartment inspection program, a practical completion inspection (PCI), also called a handover inspection, of individual apartments does not automatically establish that every common area has been inspected. Agree the levels, lobbies, corridors, stairs and other shared spaces that form part of each visit.

Takeaway: name the areas, inspect them when they are ready and report findings by level, location and trade. Keep specialist testing and statutory certification on their own tracks.

Define the common-area inspection scope before the visit

Start with the building or tower, the levels proposed for inspection and a marked plan where it helps. Use the same location names in the site brief, drawings and reports. “Level 2 lift lobby” or “stair between levels 2 and 3” gives a trade a practical destination; “common area” alone does not.

A multi-residential scope may include:

  • entrance lobbies and lift lobbies;
  • corridors, alcoves and shared cupboards;
  • internal stairs, landings and handrails;
  • visible wall, ceiling, floor and skirting finishes;
  • door frames, lift surrounds and other visible junctions;
  • agreed service-cupboard areas where access is authorised and safe; and
  • other named shared areas within the project brief.

Keep indoor common areas separate from apartment interiors, car parks, rooftops, façades and external works unless those areas are also included. GoInspect’s shared driveways and external works guide explains the separate planning needed for outdoor project areas.

Check whether each level is ready

Confirm readiness by area rather than assuming a whole tower is ready on one date. One corridor may be finished while another level still has stored materials, protective coverings or active trade work. Record areas that cannot be inspected and carry them into a later visit.

For a useful visible-finish review, surfaces should be complete, sufficiently clean and safely accessible. Ask the site team to identify incomplete work and any restrictions before the inspector arrives. This helps distinguish an unfinished area from one presented for PCI and reduces repeat visits caused only by access or preparation.

Look at finishes and their junctions

Common-area findings often occur where materials meet: the top of a skirting tile, the edge of a door frame, a lift reveal or a wall penetration. A project team needs enough detail to locate the junction and understand the visible condition without guessing at concealed construction.

In a GoInspect hallway report, the inspector recorded a gap above a skirting tile beside a stair. The report tied the photograph to the relevant level and stair location so the tiling item could be reviewed as part of that shared area.

Gap at the top of a tiled stair skirting beside a concrete step
Gap above a stair skirting tile.

Another level report recorded a chipped corner at the base of a corridor skirting tile. This is a local finish defect, but it still needs an exact level and corridor reference when similar materials repeat throughout the building.

Chipped corner at the base of a corridor skirting tile

Chipped corridor skirting tile.

Wall and ceiling finishes also need to be viewed as a route, not only as isolated photographs. The inspector can record visible chips, incomplete patches, marks or damage, while the builder reviews the appropriate repair and finish requirements. A report photograph cannot determine what is concealed behind the surface.

Marked chip in a rendered common-area wall

Chip in a rendered common-area wall.

Treat cleaning and incomplete work as reportable tasks

Final cleaning affects whether finished surfaces can be assessed and whether the shared route is ready to present. Record residue, labels, protective material or construction debris with the same care as a finish item. Describe what is visible and avoid presenting a cleaning observation as proof of damage beneath it.

The stairs below were reported for cleaning. Keeping that task under the correct stair location helps the project team direct the cleaner and then check the same route again.

Common-area stairs with cleaning residue on the treads

Cleaning residue on common-area stairs.

Choose report types that match the rectification work

GoInspect uses InspectaMate for photographic defect reporting. Each finding can retain its location, description, photographs, original item reference and relevant trade. For a multi-residential project, the same inspection records can support different reporting views.

Report view How the project team can use it
Project-area or level report Review the agreed corridor, lobby and stair findings together for a defined area.
Trade-specific report Give the tiler, renderer, cleaner or other relevant trade its items across the inspected levels.
Apartment or dwelling report Keep private-dwelling findings separate from the common-area record.
Follow-up record Retain the original item reference and record what was checked during a return visit.

Agree the required views before the program starts. Trade allocation helps route work; it does not by itself decide contractual liability. If responsibility crosses trades, the builder can coordinate the response while keeping the observation and location unchanged.

Keep specialist and certification work separate

A visual common-area defect inspection does not replace lift commissioning, fire-safety assessment, electrical or mechanical testing, access certification or statutory building certification. Where a visible item may affect a specialist system, record the observation and refer it to the appropriately qualified person.

Queensland guidance distinguishes project supervision and quality control from the building certifier’s role. The QBCC recommends project-specific supervision and quality-control inspections, including checks before handover. Business Queensland also explains that class 2 to 9 building certification inspections use a separate risk-based framework. An independent photographic report supports the site team’s QA process; it does not issue an occupancy approval.

Plan the follow-up before closing the level

After the first common-area report, keep the original item number and location when work is assigned. Ask the builder or trade to identify which items are ready for review, and arrange access to the same level or stair. A response from a trade, a completion photograph and an independent return inspection are different records, so the latest status should say what evidence supports it.

For a high-rise or multi-residential program, schedule common areas alongside the apartment batches without merging their records. GoInspect can discuss inspections organised by apartment, level, trade and agreed project area through its builder and developer quality-assurance service. To brief a new project, use the builder and developer quote form and include the building type, approximate number of levels, areas required and expected readiness sequence.